Item 27
approved contractMay 4, 2016
Description
Authorize the Bureau of Construction to enter into a contract with M.E. Latulippe Construction Inc., Ashland, NH, for the removal of the bridge that formerly carried NH Route 25 over Baker River, and modifications of the existing bridge abutments to accommodate a future bridge by others, on the basis of a low bid of $241,900. (2)Further authorize a contingency in the amount of $12,095 for payment of latent conditions which may appear during the construction of the project. Effective upon G&C approval through July 29, 2016. 100% Federal Funds.
Amount
$241,900
$241,900, $12,095
Department
DEPARTMENT OF TRANSPORTATION
Funding Source
100% Federal Funds
Vote Record
approved
Motion by Sununu, seconded by Pappas
Joseph Kenney
(R)
yes
Colin Van Ostern
(D)
yes
Christopher Sununu
(R)
yes
Christopher Pappas
(D)
yes
Dave Wheeler
(R)
yes
Documents (1)
Item_27.pdf