Item 82
approved contractMay 4, 2016
Description
Authorize the March quarterly update report on the contract with Harvey Construction (originally approved by G&C on 1-1-15, item #37), for the construction of the new Marine Patrol facility in Gilford, NH, in the amount of $7,998,171.
Amount
$8.0M
$7,998,171
Department
DEPARTMENT OF ADMINISTRATIVE SERVICES
Vendor
Harvey Construction (originally approved by G&C on 1-1-15, item #37)
for the construction of the new Marine Patrol facility in Gilford, NH
Vote Record
approved
Motion by Pappas, seconded by Kenney
Joseph Kenney
(R)
yes
Colin Van Ostern
(D)
yes
Christopher Sununu
(R)
yes
Christopher Pappas
(D)
yes
Dave Wheeler
(R)
yes
Documents (1)
Item_82.pdf
Open in new tab →