Meetings / Jan 13, 2016 / Item 46

Item 46

approved contract

Jan 13, 2016

Description

Authorize to amend a contract with Keymont Construction Inc., Laconia, NH (originally approved by G&C on 9-16-15, item #59), for additional clarifier turntable repairs at the Franklin Wastewater Treatment Facility, by increasing the amount by $7,073.65 to $56,073.75 from $49,000, and by extending the contract period to March 31, 2016 from December 31, 2015. 100% WRBP Funds.

Amount
$56,074
$7,073.65, $56,073.75, $49,000,
Vendor
Keymont Construction Inc.
Laconia, NH
Funding Source
100% WRBP Funds
Vote Record approved
Joseph Kenney (R) yes
Colin Van Ostern (D) yes
Christopher Sununu (R) yes
Christopher Pappas (D) yes
Dave Wheeler (R) yes

Documents (1)

Item_46.pdf Open in new tab →
← Back to Jan 13, 2016 meeting