Item 29
approved contractAug 26, 2015
Description
Authorize the Bureau of Construction to enter into a contract with D.L. King & Associates Inc., Nashua, NH, for a new fueling facility at the Littleton Shed, on the basis of a single bid of $559,840. Effective upon G&C approval through November 20, 2015, unless extended by the Department in accordance with the Standard Specifications. (2)Further authorize a contingency in the amount of $27,992 for payment of latent conditions, which may appear during the construction of the project. 100% Capital Budget Funds.
Amount
$559,840
$559,840, $27,992
Department
DEPARTMENT OF TRANSPORTATION
Funding Source
100% Capital Budget Funds
Vote Record
approved