Meetings / Jun 10, 2015 / Item 122

Item 122

approved contract late item

Jun 10, 2015

Description

Authorize the Bureau of Public Works Design and Construction to amend a contract with Eckman Construction Company Inc., Bedford, NH (originally approved by G&C on 7-16-14, item #39), for the Regional Training Institute and Barracks Facility, by increasing the contingency for rework of unforeseen and latent conditions by $75,000 from $1,380,575 to $1,455,575, the contingency increase will increase the total not to exceed price from $28,992,075 to $29,067,075. Effective upon G&C approval. 100% Capital – General Funds.

Amount
$29.1M
$75,000, $1,380,575, $1,455,575,, $28,992,075, $29,067,075
Funding Source
100% Capital
Vote Record approved
Joseph Kenney (R) yes
Colin Van Ostern (D) yes
Christopher Sununu (R) yes
Christopher Pappas (D) yes
Dave Wheeler (R) yes