Meetings / May 27, 2015 / Item 44

Item 44

approved contract late item

May 27, 2015

Description

Authorize the Bureau of Construction to enter into a contract with Annseal Inc., Johnson City, NY, for full width crack seal treatment along 18 miles of I-93 and ramps in the Towns of Tilton, Sanbornton, Meredith, New Hampton, and Ashland, on the basis of a low bid of $391,195.50. (2)Further authorize a contingency in the amount of $27,383.69 for payment of latent conditions which may appear during the construction of the project. Effective upon G&C approval through August 28, 2015. 100% Federal Funds.

Amount
$391,196
$391,195.50, $27,383.69
Vendor
Annseal Inc.
Johnson City, NY
Funding Source
100% Federal Funds
Vote Record approved
Motion by Sununu, seconded by Wheeler
Joseph Kenney (R) yes
Colin Van Ostern (D) yes
Christopher Sununu (R) yes
Christopher Pappas (D) yes
Dave Wheeler (R) yes

Documents (1)

Item_44.pdf Open in new tab →
← Back to May 27, 2015 meeting