Meetings / Mar 25, 2015 / Item 22

Item 22

approved contract

Mar 25, 2015

Description

Authorize the Bureau of Construction to enter into a contract with R.S. Audley Inc., Bow, NH, for replacing the existing concrete bridge deck on the Hooksett Toll Plaza Access Road over the I-93 Exit 11 northbound off-ramp in Hooksett, on the basis of a low bid of $539,443.90. (2)Further authorize a contingency in the amount of $26,972.20 for payment of latent conditions, which may appear during the construction of the project. Effective upon G&C approval through October 2, 2015. 100% Turnpike Funds.

Amount
$539,444
$539,443.90, $26,972.20
Vendor
R.S. Audley Inc.
Bow, NH
Funding Source
100% Turnpike Funds
Vote Record approved
Motion by Kenney, seconded by Sununu
Joseph Kenney (R) yes
Colin Van Ostern (D) yes
Christopher Sununu (R) yes
Christopher Pappas (D) yes
Dave Wheeler (R) yes

Documents (1)

Item_22.pdf Open in new tab →