Meetings / Feb 25, 2015 / Item 68

Item 68

approved contract

Feb 25, 2015

Description

Authorize the Bureau of Public Works Design and Construction to retroactively enter into a contract with D.L. King & Associates Inc., Nashua, NH, for the Walk-in Freezer Replacement – Surplus Distribution Facility, Concord, NH, for a total price not to exceed $169,900. Effective February 6, 2015 through June 30, 2015. 55% Federal, 45% Capital – General Funds. (2)Further authorize the amount of $7,640 for payment to the Department of Administrative Services, Bureau of Public Works Design and Construction, Capital Clerk for oversight and engineering services provided, bringing the total to $177,540. 100% Capital – General Funds.

Amount
$177,540
$169,900, $7,640, $177,540
Vendor
D.L. King & Associates Inc.
Nashua, NH
Funding Source
55% Federal; 45% Capital; 100% Capital
Vote Record approved
Motion by Kenney, seconded by Sununu
Joseph Kenney (R) yes
Colin Van Ostern (D) yes
Christopher Sununu (R) yes
Christopher Pappas (D) yes
Dave Wheeler (R) yes

Documents (1)

Item_68.pdf Open in new tab →