Authorize the Bureau of Construction to enter into a contract with Busby Construction Co Inc., Atkinson, NH, for repairs to outlet/inlet pipes, culvert headwalls and scour protection at 13 culvert and slope pipes, located on the F. E. Everett Turnpike in Nashua, Merrimack, Manchester, Hooksett, Bow and Concord, on the basis of a low bid of $494,335.50. (2)Further authorize a contingency in the amount of $24,716.78 for payment of latent conditions, which may appear during the construction of the project. Effective upon G&C approval through September 25, 2015. 100% Turnpike Funds.

Amount
$494,336
$494,335.50, $24,716.78
Vendor
Busby Construction Co Inc.
Atkinson, NH
Funding Source
100% Turnpike Funds
Vote Record approved
Joseph Kenney (R) yes
Colin Van Ostern (D) yes
Christopher Sununu (R) yes
Christopher Pappas (D) yes
Dave Wheeler (R) yes

Documents (1)

Item_23.pdf Open in new tab →
← Back to Feb 11, 2015 meeting