Meetings / Oct 15, 2014 / Item 19

Item 19

approved nomination

Oct 15, 2014

Description

Authorize the Bureau of Construction to amend a contract with Pike Industries Inc., Belmont, NH (originally approved by G&C on 6-18-14, item #196), for pavement rehabilitation of approximately 3 miles of US Route 3 in the Town of Pittsburg, by increasing the amount by $160,000 from $2,943,151.98 to $3,103,151.98, and by extending the completion date from October 17, 2014 through May 30, 2015. 100% Federal Funds.

Amount
$3.1M
$160,000, $2,943,151.98, $3,103,151.98
Vendor
Pike Industries Inc.
Belmont, NH
Funding Source
100% Federal Funds
Effective Dates
October 17, 2014 — May 30, 2015
Vote Record approved
Motion by Pappas, seconded by Pignatelli voted to confirm the
Joseph Kenney (R) yes
Colin Van Ostern (D) yes
Christopher Sununu (R) yes
Christopher Pappas (D) yes
Debora Pignatelli (D) yes

Documents (1)