Item 23
approved contractOct 1, 2014
Description
Authorize the Bureau of Construction to enter into a contract with R.M. Piper Inc., Plymouth, NH, for removing the toll plazas at the Exit 12, Bedford Road interchange on the F.E. Everett Turnpike in Merrimack, NH, on the basis of a low bid of $388,891. (2)Further authorize a contingency in the amount of $19,444.55 for payment of latent conditions which may appear during the construction of the project. Effective upon G&C approval through December 12, 2014. 100% Turnpike Funds.
Amount
$388,891
$388,891, $19,444.55
Department
DEPARTMENT OF TRANSPORTATION
Funding Source
100% Turnpike Funds
Vote Record
approved
Joseph Kenney
(R)
yes
Colin Van Ostern
(D)
yes
Christopher Sununu
(R)
yes
Christopher Pappas
(D)
yes
Debora Pignatelli
(D)
yes
Documents (1)
Item_23.pdf
Open in new tab →