Meetings / Oct 1, 2014 / Item 23

Item 23

approved contract

Oct 1, 2014

Description

Authorize the Bureau of Construction to enter into a contract with R.M. Piper Inc., Plymouth, NH, for removing the toll plazas at the Exit 12, Bedford Road interchange on the F.E. Everett Turnpike in Merrimack, NH, on the basis of a low bid of $388,891. (2)Further authorize a contingency in the amount of $19,444.55 for payment of latent conditions which may appear during the construction of the project. Effective upon G&C approval through December 12, 2014. 100% Turnpike Funds.

Amount
$388,891
$388,891, $19,444.55
Vendor
R.M. Piper Inc.
Plymouth, NH
Funding Source
100% Turnpike Funds
Vote Record approved
Joseph Kenney (R) yes
Colin Van Ostern (D) yes
Christopher Sununu (R) yes
Christopher Pappas (D) yes
Debora Pignatelli (D) yes

Documents (1)

Item_23.pdf Open in new tab →
← Back to Oct 1, 2014 meeting