Meetings / Sep 3, 2014 / Item 132

Item 132

approved contract consent calendar

Sep 3, 2014

Description

Authorize the Bureau of Public Works Design and Construction to enter into a contract with Coreno Construction Co., Inc., Portsmouth, NH, for the Cooling Tower and Roof Replacement at the Rockingham County Courthouse in Brentwood, NH, for a total price not to exceed $805,000. Effective upon G&C approval through July 31, 2015. 88% Capital-General, 12% Operating-General Funds.

Amount
$805,000
$805,000
Vendor
Coreno Construction Co., Inc.
Portsmouth, NH
Funding Source
88% Capital; 12% Operating
Vote Record approved
Motion by Pappas, seconded by Van Ostern
Joseph Kenney (R) yes
Colin Van Ostern (D) yes
Christopher Sununu (R) yes
Christopher Pappas (D) yes
Debora Pignatelli (D) yes

Documents (1)

Item_132.pdf Open in new tab →
← Back to Sep 3, 2014 meeting