Meetings / Jul 16, 2014 / Item 38

Item 38

approved contract consent calendar late item

Jul 16, 2014

Description

Authorize the Bureau of Public Works Design and Construction to enter into a contract with Project Resource Group LLC, Francestown, NH, for mechanical upgrades and roofing, statewide, for a total price not to exceed $456,221. Effective upon G&C approval through February 15, 2015. 75% Capital – Other – (Fire Academy Bldg. Upgrades and Critical Maintenance), 2% Capital – Highway, 19% Capital – General, 4% Other – Transfer Funds. (2)Further authorize to pay the amount of $14,953 to the Department of Administrative Services, Bureau of Public Works Design and Construction, Capital Clerk for oversight and engineering services provided, bringing the total to $471,174. 100% Capital – General Funds. (3)Further authorize the amount of $7,550 for payment to the Department of Administrative Services, Bureau of Public Works Design and Construction, for engineering services provided, bringing the total to $478,724. 66% Other (Fire Standards & EMS Administrator), 17% Capital – General, 17% Transfer Funds.

Amount
$478,724
$456,221, $14,953, $471,174, $7,550, $478,724
Vendor
Project Resource Group LLC
Francestown, NH
Funding Source
75% Capital; 2% Capital; 19% Capital; 4% Other; 100% Capital; 66% Other (Fire Standards; 17% Capital; 17% Transfer Funds
Vote Record approved
Joseph Kenney (R) yes
Colin Van Ostern (D) yes
Christopher Sununu (R) yes
Christopher Pappas (D) yes
Debora Pignatelli (D) yes

Documents (1)

Item_38.pdf Open in new tab →