approved contract

Jul 2, 2014

Description

Authorize the Bureau of Construction to enter into a contract with R.S. Audley Inc., Bow, NH, for replacing the existing red list bridge that carries NH Route 3A over Interstate 93 at Exit 12 in Concord, on the basis of a low bid of $5,844,689.91. (2)Further authorize a contingency in the amount of $292,234.50 for payment of latent conditions which may appear during the construction of the project. Effective upon G&C approval through June 10, 2016. 100% Turnpike Funds.

Amount
$5.8M
$5,844,689.91, $292,234.50
Vendor
R.S. Audley Inc.
Bow, NH
Funding Source
100% Turnpike Funds