Item 65
approved contract consent calendarMar 12, 2014
Description
Authorize to enter into a contract with T. Buck Construction Inc., Auburn, ME, for rehabilitation of the red list bridge carrying NH 31 over the Souhegan River in the Town of Wilton, on the basis of a low bid of $884,930. (2)Further authorize a contingency in the amount of $44,246.50 for payment of latent conditions, which may appear during the construction of the project. Effective upon G&C approval through September 26, 2014. 100% Federal Funds.
Amount
$884,930
$884,930, $44,246.50
Department
DEPARTMENT OF TRANSPORTATION
Funding Source
100% Federal Funds
Vote Record
approved