Meetings / Sep 18, 2013 / Item 76

Item 76

approved contract consent calendar

Sep 18, 2013

Description

Authorize the Bureau of Construction to enter into a contract with S.U.R Construction Inc., Rochester, NH, for roadway rehabilitation and widening on NH 28 at its intersection with Stockbridge Corner Road in Alton, on the basis of a low bid of $1,491,495. (2)Further authorize a contingency in the amount of $149,149.50 for payment of latent conditions which may appear during the construction of the project. Effective upon G&C approval through October 17, 2014. 100% Federal Funds.

Amount
$1.5M
$1,491,495, $149,149.50
Vendor
S.U.R Construction Inc.
Rochester, NH
Funding Source
100% Federal Funds
Vote Record approved
Raymond Burton (R) yes
Colin Van Ostern (D) yes
Christopher Sununu (R) yes
Christopher Pappas (D) yes
Debora Pignatelli (D) yes

Documents (1)

Item_76.pdf Open in new tab →