Item 34
approved contractApr 9, 2025
Description
Authorize the Bureau of Highway Design to amend a sole source contract with Vanasse Hangen Brustlin, Inc., Bedford, NH, for intersection improvements in the Town of Jaffrey, NH, by increasing the fee by $456,258.18 from $2,655,655.85 to $3,111,924.03, with no change to the completion date of June 30, 2028. Effective upon G&C approval. 100% Federal Funds
Amount
$3.1M
$456,258.18, $2,655,655.85, $3,111,924.03
Department
DEPARTMENT OF TRANSPORTATION
Funding Source
100% Federal Funds
Vote Record
approved
Motion by Stevens, seconded by Liot Hill acted as follows
Joseph Kenney
(R)
yes
Karen Liot Hill
(D)
yes
Janet Stevens
(R)
yes
John Stephen
(R)
yes
Dave Wheeler
(R)
yes
Documents (1)
Item_34.pdf