Meetings / Jul 24, 2013 / Item 53

Item 53

approved amendment

Jul 24, 2013

Description

Authorize to amend an agreement with Inter-Fluve Inc., (originally approved by G&C on 6-22-11, item #96), to complete the Geomorphology-Based Restoration Design and Permitting for the Suncook River and Floodplain project, by changing the Scope of Services, by increasing the award by $10,000 from $408,851 to $418,851 and by extending the completion date to December 31, 2013 from September 30, 2013. 100% Capital (General) Funds.

Amount
$418,851
$10,000, $408,851, $418,851
Funding Source
100% Capital (General) Funds
Vote Record approved
Raymond Burton (R) yes
Colin Van Ostern (D) yes
Christopher Sununu (R) yes
Christopher Pappas (D) yes
Debora Pignatelli (D) yes

Documents (1)

Item_53.pdf Open in new tab →
← Back to Jul 24, 2013 meeting