Item 40
approved contract consent calendarJun 19, 2013
Description
Authorize the Bureau of Public Works Design and Construction to add a contingency for unforeseen and latent conditions, in the amount of $275,000 to the contract with North Branch Construction Inc., Concord, NH (originally approved by G&C on 5-1-13, item #22, in the amount of $2,161,570), for exterior Building Improvements – Acute Psychiatric Services Facility, Concord, NH, for a total of $2,436,570. Effective upon G&C approval through November 1, 2013. 100% Capital – General Funds.
Amount
$2.4M
$275,000, $2,161,570, $2,436,570
Department
DEPARTMENT OF ADMINISTRATIVE SERVICES
Funding Source
100% Capital
Vote Record
approved