Meetings / Jun 19, 2013 / Item 42C

Item 42C

approved contract consent calendar late item

Jun 19, 2013

Description

Authorize the Bureau of Public Works Design and Construction to enter into a contract with R.J. Olszak Construction Inc., d/b/a All-Ways Recycling-Wrecking, Bridgewater, NH, for the demolition of 2 above-ground storage tanks at the Youth Development Center, Manchester, NH, in an amount not to exceed $29,950. Effective upon G&C approval through august 30, 2013. 100% General – Operating Funds.

Amount
$29,950
$29,950
Funding Source
100% General
Vote Record approved
Raymond Burton (R) yes
Colin Van Ostern (D) yes
Christopher Sununu (R) yes
Christopher Pappas (D) yes
Debora Pignatelli (D) yes
Related Sub-Items (42)
42
Authorize the Bureau of Public Works Design and Construction to enter into a contract with KPMB, Bow, NH, for the Mechanical Upgrades, Statewide, for a total price not to exceed $280,700. Effective up
$303,500 approved
42
Authorize the Bureau of Public Works Design and Construction to enter into a contract with KPMB, Bow, NH, for the Mechanical Upgrades, Statewide, for a total price not to exceed $280,700. Effective up
$303,500 approved
42
Authorize the Bureau of Public Works Design and Construction to enter into a contract with KPMB, Bow, NH, for the Mechanical Upgrades, Statewide, for a total price not to exceed $280,700. Effective up
$303,500 approved
42
Authorize the Bureau of Public Works Design and Construction to enter into a contract with KPMB, Bow, NH, for the Mechanical Upgrades, Statewide, for a total price not to exceed $280,700. Effective up
$303,500 approved
42
Authorize the Bureau of Public Works Design and Construction to enter into a contract with KPMB, Bow, NH, for the Mechanical Upgrades, Statewide, for a total price not to exceed $280,700. Effective up
$303,500 approved
42
Authorize the Bureau of Public Works Design and Construction to enter into a contract with KPMB, Bow, NH, for the Mechanical Upgrades, Statewide, for a total price not to exceed $280,700. Effective up
$303,500 approved
42
Authorize the Bureau of Public Works Design and Construction to enter into a contract with KPMB, Bow, NH, for the Mechanical Upgrades, Statewide, for a total price not to exceed $280,700. Effective up
$303,500 approved
42A
Authorize the Bureau of Public Works Design and Construction to amend contracts with Turnstone Corp.; Wesfield Construction Co.; and James J. Welch & Co. Inc., (respectively approved by G&C on 5-26-10
$279,912 approved
42A
Authorize the Bureau of Public Works Design and Construction to amend contracts with Turnstone Corp.; Wesfield Construction Co.; and James J. Welch & Co. Inc., (respectively approved by G&C on 5-26-10
$279,912 approved
42A
Authorize the Bureau of Public Works Design and Construction to amend contracts with Turnstone Corp.; Wesfield Construction Co.; and James J. Welch & Co. Inc., (respectively approved by G&C on 5-26-10
$279,912 approved
42A
Authorize the Bureau of Public Works Design and Construction to amend contracts with Turnstone Corp.; Wesfield Construction Co.; and James J. Welch & Co. Inc., (respectively approved by G&C on 5-26-10
$279,912 approved
42A
Authorize the Bureau of Public Works Design and Construction to amend contracts with Turnstone Corp.; Wesfield Construction Co.; and James J. Welch & Co. Inc., (respectively approved by G&C on 5-26-10
$279,912 approved
42A
Authorize the Bureau of Public Works Design and Construction to amend contracts with Turnstone Corp.; Wesfield Construction Co.; and James J. Welch & Co. Inc., (respectively approved by G&C on 5-26-10
$279,912 approved
42A
Authorize the Bureau of Public Works Design and Construction to amend contracts with Turnstone Corp.; Wesfield Construction Co.; and James J. Welch & Co. Inc., (respectively approved by G&C on 5-26-10
$279,912 approved
42B
Authorize to pay the National Association of State Budget Officers, Washington, DC, in an amount not to exceed $13,550 for Fiscal Year 2014 membership. Effective July 1, 2013 through June 30, 2014. 10
$13,550 approved
42B
Authorize to pay the National Association of State Budget Officers, Washington, DC, in an amount not to exceed $13,550 for Fiscal Year 2014 membership. Effective July 1, 2013 through June 30, 2014. 10
$13,550 approved
42B
Authorize to pay the National Association of State Budget Officers, Washington, DC, in an amount not to exceed $13,550 for Fiscal Year 2014 membership. Effective July 1, 2013 through June 30, 2014. 10
$13,550 approved
42B
Authorize to pay the National Association of State Budget Officers, Washington, DC, in an amount not to exceed $13,550 for Fiscal Year 2014 membership. Effective July 1, 2013 through June 30, 2014. 10
$13,550 approved
42B
Authorize to pay the National Association of State Budget Officers, Washington, DC, in an amount not to exceed $13,550 for Fiscal Year 2014 membership. Effective July 1, 2013 through June 30, 2014. 10
$13,550 approved
42B
Authorize to pay the National Association of State Budget Officers, Washington, DC, in an amount not to exceed $13,550 for Fiscal Year 2014 membership. Effective July 1, 2013 through June 30, 2014. 10
$13,550 approved
42B
Authorize to pay the National Association of State Budget Officers, Washington, DC, in an amount not to exceed $13,550 for Fiscal Year 2014 membership. Effective July 1, 2013 through June 30, 2014. 10
$13,550 approved
42D
Authorize the Bureau of Public Works Design and Construction to amend a consultant agreement with Corzilius, Matuszewski, Krause Architects, PA (originally approved by G&C on 6-17-09, item #25), for a
approved
42D
Authorize the Bureau of Public Works Design and Construction to amend a consultant agreement with Corzilius, Matuszewski, Krause Architects, PA (originally approved by G&C on 6-17-09, item #25), for a
approved
42D
Authorize the Bureau of Public Works Design and Construction to amend a consultant agreement with Corzilius, Matuszewski, Krause Architects, PA (originally approved by G&C on 6-17-09, item #25), for a
approved
42D
Authorize the Bureau of Public Works Design and Construction to amend a consultant agreement with Corzilius, Matuszewski, Krause Architects, PA (originally approved by G&C on 6-17-09, item #25), for a
approved
42D
Authorize the Bureau of Public Works Design and Construction to amend a consultant agreement with Corzilius, Matuszewski, Krause Architects, PA (originally approved by G&C on 6-17-09, item #25), for a
approved
42D
Authorize the Bureau of Public Works Design and Construction to amend a consultant agreement with Corzilius, Matuszewski, Krause Architects, PA (originally approved by G&C on 6-17-09, item #25), for a
approved
42D
Authorize the Bureau of Public Works Design and Construction to amend a consultant agreement with Corzilius, Matuszewski, Krause Architects, PA (originally approved by G&C on 6-17-09, item #25), for a
approved
42E
Authorize the Bureau of Public Works Design and Construction to enter into a contract with Knowles Industrial Services Corp., Gorham, ME, for the YDC Boiler House Smokestack Repair, Manchester, NH, fo
$201,480 approved
42E
Authorize the Bureau of Public Works Design and Construction to enter into a contract with Knowles Industrial Services Corp., Gorham, ME, for the YDC Boiler House Smokestack Repair, Manchester, NH, fo
$201,480 approved
42E
Authorize the Bureau of Public Works Design and Construction to enter into a contract with Knowles Industrial Services Corp., Gorham, ME, for the YDC Boiler House Smokestack Repair, Manchester, NH, fo
$201,480 approved
42E
Authorize the Bureau of Public Works Design and Construction to enter into a contract with Knowles Industrial Services Corp., Gorham, ME, for the YDC Boiler House Smokestack Repair, Manchester, NH, fo
$201,480 approved
42E
Authorize the Bureau of Public Works Design and Construction to enter into a contract with Knowles Industrial Services Corp., Gorham, ME, for the YDC Boiler House Smokestack Repair, Manchester, NH, fo
$201,480 approved
42E
Authorize the Bureau of Public Works Design and Construction to enter into a contract with Knowles Industrial Services Corp., Gorham, ME, for the YDC Boiler House Smokestack Repair, Manchester, NH, fo
$201,480 approved
42E
Authorize the Bureau of Public Works Design and Construction to enter into a contract with Knowles Industrial Services Corp., Gorham, ME, for the YDC Boiler House Smokestack Repair, Manchester, NH, fo
$201,480 approved
42F
Authorize to amend a contract with First Data Services LLC, CO, (originally approved by G&C on 7-16-08, item #23), for Merchant Card Processing services, by extending the completion date from June 30,
approved
42F
Authorize to amend a contract with First Data Services LLC, CO, (originally approved by G&C on 7-16-08, item #23), for Merchant Card Processing services, by extending the completion date from June 30,
approved
42F
Authorize to amend a contract with First Data Services LLC, CO, (originally approved by G&C on 7-16-08, item #23), for Merchant Card Processing services, by extending the completion date from June 30,
approved
42F
Authorize to amend a contract with First Data Services LLC, CO, (originally approved by G&C on 7-16-08, item #23), for Merchant Card Processing services, by extending the completion date from June 30,
approved
42F
Authorize to amend a contract with First Data Services LLC, CO, (originally approved by G&C on 7-16-08, item #23), for Merchant Card Processing services, by extending the completion date from June 30,
approved
42F
Authorize to amend a contract with First Data Services LLC, CO, (originally approved by G&C on 7-16-08, item #23), for Merchant Card Processing services, by extending the completion date from June 30,
approved
42F
Authorize to amend a contract with First Data Services LLC, CO, (originally approved by G&C on 7-16-08, item #23), for Merchant Card Processing services, by extending the completion date from June 30,
approved

Documents (7)

Item_42.pdf Open in new tab →
Item_42A.pdf (42A) Open in new tab →
Item_42B.pdf (42B) Open in new tab →
Item_42C.pdf (42C) Open in new tab →
Item_42D.pdf (42D) Open in new tab →
Item_42E.pdf (42E) Open in new tab →
Item_42F.pdf (42F) Open in new tab →
← Back to Jun 19, 2013 meeting