Meetings / Jun 5, 2013 / Item 24

Item 24

approved contract consent calendar

Jun 5, 2013

Description

Authorize the Bureau of Public Works Design and Construction to enter into a contract with Pellowe Construction LLC, Alton, NH, for the Main Building ADA Restroom Upgrades and Window Replacement – Governor Hugh Gallen State Office Park, Concord, NH, for a total price not to exceed $861,520. Effective upon G&C approval through November 1, 2013. 36% Capital – General, 48% Other, 16% Federal Funds. (2)Further authorize a contingency in the amount of $29,800 for unforeseen expenses related to structural and water damage, bringing the total to $891,320. 100% Capital – General Funds. (3)Further authorize the amount of $42,500 for payment to the Department of Administrative Services, Bureau of Public Works Design and Construction, for engineering services and capital clerk provided, bringing the total to $933,820. 83% General – Capital, 17% Federal Funds.

Amount
$933,820
$861,520, $29,800, $891,320, $42,500, $933,820
Vendor
Pellowe Construction LLC
Alton, NH
Funding Source
36% Capital; 48% Other; 16% Federal Funds; 100% Capital; 83% General; 17% Federal Funds
Vote Record approved
Raymond Burton (R) yes
Colin Van Ostern (D) yes
Christopher Sununu (R) yes
Christopher Pappas (D) yes
Debora Pignatelli (D) yes

Documents (1)

Item_24.pdf Open in new tab →