Meetings / Jun 5, 2013 / Item 206

Item 206

approved contract consent calendar late item

Jun 5, 2013

Description

Authorize the Bureau of Construction to enter into a contract with New York Bituminous Products Corp., Chester, NY, for pavement preservation resurfacing treatment along a section of I-93 and of I-293 roadway in Manchester, on the basis of a low bid of $1,648,844. (2)Further authorize a contingency in the amount of $164,884.40 for payment of latent conditions which may appear during the construction of the project. Effective upon G&C approval through September 6, 2013. 100% Federal Funds.

Amount
$1.6M
$1,648,844, $164,884.40
Funding Source
100% Federal Funds
Vote Record approved
Motion by Burton, seconded by Pappas
Raymond Burton (R) yes
Colin Van Ostern (D) yes
Christopher Sununu (R) yes
Christopher Pappas (D) yes
Debora Pignatelli (D) yes

Documents (1)

Item_206.pdf Open in new tab →
← Back to Jun 5, 2013 meeting