approved contract consent calendar late itemJun 5, 2013
Description
Authorize the Bureau of Construction to enter into a contract with Busby Construction Co., Inc., Atkinson, NH, for sliplining an existing corrugated metal arc pipe carrying Kelly Brook under NH Route 121A in Plaistow, on the basis of a low bid of $128,136.25. (2)Further authorize a contingency in the amount of $12,813.63 for payment of latent conditions which may appear during the construction of the project. Effective upon G&C approval through August 16, 2013. 100% Federal Funds.
Amount
$128,136
$128,136.25, $12,813.63
Department
DEPARTMENT OF TRANSPORTATION
Funding Source
100% Federal Funds
Vote Record
approved
Motion by Burton, seconded by Pappas
Raymond Burton
(R)
yes
Colin Van Ostern
(D)
yes
Christopher Sununu
(R)
yes
Christopher Pappas
(D)
yes
Debora Pignatelli
(D)
yes