Meetings / May 1, 2013 / Item 113

Item 113

approved contract consent calendar

May 1, 2013

Description

Authorize the Bureau of Construction to enter into a contract with F.L. Merrill Construction, Inc., Pembroke, NH, for culvert replacement and roadway reconstruction for Mitchell Brook, located on US Route 4/NH Route 11 in Andover, on the basis of a low bid of $467,727.85. (2)Further authorize a contingency in the amount of $23,386.39 for payment of latent conditions, which may appear during the construction of the project. Effective upon G&C approval through September 20, 2013. 83% Federal, 17% Betterment Funds.

Amount
$467,728
$467,727.85, $23,386.39
Vendor
F.L. Merrill Construction, Inc.
Pembroke, NH
Funding Source
83% Federal; 17% Betterment Funds
Vote Record approved
Raymond Burton (R) yes
Colin Van Ostern (D) yes
Christopher Sununu (R) yes
Christopher Pappas (D) yes
Debora Pignatelli (D) yes

Documents (1)

Item_113.pdf Open in new tab →
← Back to May 1, 2013 meeting