Item 113
approved contract consent calendarMay 1, 2013
Description
Authorize the Bureau of Construction to enter into a contract with F.L. Merrill Construction, Inc., Pembroke, NH, for culvert replacement and roadway reconstruction for Mitchell Brook, located on US Route 4/NH Route 11 in Andover, on the basis of a low bid of $467,727.85. (2)Further authorize a contingency in the amount of $23,386.39 for payment of latent conditions, which may appear during the construction of the project. Effective upon G&C approval through September 20, 2013. 83% Federal, 17% Betterment Funds.
Amount
$467,728
$467,727.85, $23,386.39
Department
DEPARTMENT OF TRANSPORTATION
Funding Source
83% Federal; 17% Betterment Funds
Vote Record
approved
Raymond Burton
(R)
yes
Colin Van Ostern
(D)
yes
Christopher Sununu
(R)
yes
Christopher Pappas
(D)
yes
Debora Pignatelli
(D)
yes
Documents (1)