approved contract late item

Mar 20, 2013

Description

Authorize the Bureau of Construction to amend a contract with Weaver Brothers Construction Inc., Concord, NH (originally approved by G&C on 10-17-12, item #98), for the installation of a median barrier at a number of locations on Interstate 89 from the Interstate 93 interchange in Bow to the exit 5 interchange in Hopkinton, by increasing the amount by $275,000 from $1,915,786.72 to $2,190,786.72. Effective upon G&C approval. 100% Federal Funds.

Amount
$2.2M
$275,000, $1,915,786.72, $2,190,786.72
Funding Source
100% Federal Funds
Vote Record approved
Raymond Burton (R) yes
Colin Van Ostern (D) yes
Christopher Sununu (R) yes
Christopher Pappas (D) yes
Debora Pignatelli (D) yes

Documents (1)

Item_86.pdf Open in new tab →