approved contract consent calendar late item

Jan 16, 2013

Description

Authorize to retroactively amend a sole source agreement with Inter-Fluve Inc., (originally approved by G&C on 6-22-11, item #96), to complete the Geomorphology-Based Restoration Design and Permitting for the Suncook River and Floodplain project, to include additional Tasks, by increasing the amount by $72,851 from $336,000 to $408,851, and by extending the completion date to September 30, 2013 from December 31, 2012. 100% Other (Interagency Pass-Thru Federal) Funds.

Vote Record approved
Motion by Sununu, seconded by Burton authorized the
Raymond Burton (R) yes
Colin Van Ostern (D) yes
Christopher Sununu (R) yes
Christopher Pappas (D) yes
Debora Pignatelli (D) yes