Meetings / Dec 19, 2012 / Item 95

Item 95

approved contract consent calendar late item

Dec 19, 2012

Description

Authorize the Bureau of Construction to enter into a contract with Connie’s Septic Service Inc., d/b/a C.S.S.I., Bedford, NH, for design, permitting, construction, start-up, and placement of a septic system replacement in service for the existing NHDOT Rest Area (I-93 southbound) in Sanbornton, on the basis of a low bid of $117,000. (2)Further authorize the amount of $2,300 for payment to the Department of Administrative Services, Bureau of Public Works Design and Construction, for engineering services provided, bringing the total to $119,300. Effective upon G&C approval through May 17, 2013. 100% Federal Funds. 11 #96 Authorize the Bureau of Construction to enter into a contract with Continental Paving Inc., Londonderry, NH, for 11 miles of pavement overlay on NH Route 49 in Campton and on Tripoli Road in Waterville Valley, on the basis of a low bid of $890,856. (2)Further authorize a contingency in the amount of $62,359.92 for payment of latent conditions which may appear during the construction of the project. Effective upon G&C approval through August 2, 2013. 100% Federal Funds. #97 Authorize the Bureau of Construction to enter into a contract with Delucca Fence Company Inc., Methuen, MA, for replacement of substandard cable guardrail along the NH Rte 12 corridor in the Town of Walpole, on the basis of a low bid of $951,738.37. (2)Further authorize a contingency in the amount of $95,173.84 for payment of latent conditions which may appear during the construction of the project. Effective upon G&C approval through June 28, 2013. 100% Federal Funds. #98 Authorize the Bureau of Construction to enter into a contract with Reed & Reed Inc., Woolwich, ME, for bridge rehabilitation on Interstate 93 over the Connecticut River between Littleton, NH and Waterford, VT, on the basis of a low bid of $8,189,764.20. (2)Further authorize a contingency in the amount of $573,283.48 for payment of latent conditions which may appear during the construction of the project. Effective upon G&C approval through October 31, 2014. 100% Federal Funds.

Amount
$8.2M
$117,000, $2,300, $119,300, $890,856, $62,359.92, $951,738.37, $95,173.84, $8,189,764.20, $573,283.48
Funding Source
100% Federal Funds; 100% Federal Funds; 100% Federal Funds; 100% Federal Funds
Vote Record approved
Motion by St. Hilaire, seconded by Sununu authorized
Raymond Burton (R) yes
Daniel St. Hilaire (R) yes
Christopher Sununu (R) yes
Raymond Wieczorek (R) yes
Dave Wheeler (R) yes