Item 98
approved contract late itemOct 17, 2012
Description
Authorize the Bureau of Construction to enter into a contract with Weaver Bros. Construction Co., Inc., Concord, NH, for installation of median barrier at a number of locations on Interstate 93 interchange in Bow and the Exit 5 interchange in Hopkinton, on the basis of a low bid of $1,915,786.72. (2)Further authorize a contingency in the amount of $95,789.34 for payment of latent conditions which may appear during the construction of the project. Effective upon G&C approval through August 23, 2013. 100% Federal Funds.
Amount
$1.9M
$1,915,786.72, $95,789.34
Department
DEPARTMENT OF TRANSPORTATION
Funding Source
100% Federal Funds
Vote Record
approved
Raymond Burton
(R)
yes
Daniel St. Hilaire
(R)
yes
Christopher Sununu
(R)
yes
Raymond Wieczorek
(R)
yes
Dave Wheeler
(R)
yes