Meetings / Apr 18, 2012 / Item 87

Item 87

approved amendment consent calendar late item

Apr 18, 2012

Description

Authorize to amend the memorandum of agreement with the Fish and Game Department (originally approved by G&C on 9-22-10, item #126), to complete remaining repairs to Akers Pond Dam in Errol, by extending the completion date from June 30, 2012 to June 30, 2015. No Additional Funding. 100% Dam Project Funds.

Vendor
Fish and Game Department (originally approved by G&C on 9-22-10, item #126)
to complete remaining repairs to Akers Pond Dam in Errol, by
Funding Source
100% Dam Project Funds
Effective Dates
June 30, 2012 — June 30, 2015
Vote Record approved
Motion by Wieczorek, seconded by Burton authorized
Raymond Burton (R) yes
Daniel St. Hilaire (R) yes
Christopher Sununu (R) yes
Raymond Wieczorek (R) yes
Dave Wheeler (R) yes
← Back to Apr 18, 2012 meeting