Item 134
approved contract consent calendar late itemMar 28, 2012
Description
Authorize the Bureau of Construction to amend a contract with E.D. Swett Inc., Concord, NH, (originally approved by G&C on 7-14-10, item #112), for the replacement of bridge decks on the I-93 bridges over the Merrimack River, rehabilitation of the I-93 bridges over NH Route 3A at Exit 10, and pavement rehabilitation in the City of Manchester and the Town of Hooksett, by increasing the amount by $690,000 from $11,980,055.85 to $12,670,055.85 100% Federal Funds.
Amount
$12.7M
$690,000, $11,980,055.85, $12,670,055.85
Department
DEPARTMENT OF TRANSPORTATION
Funding Source
100% Federal Funds
Vote Record
approved
Motion by Burton, seconded by St
Raymond Burton
(R)
yes
Daniel St. Hilaire
(R)
yes
Christopher Sununu
(R)
yes
Raymond Wieczorek
(R)
yes
Dave Wheeler
(R)
yes