Meetings / Feb 22, 2012 / Item 78

Item 78

approved contract consent calendar

Feb 22, 2012

Description

Authorize the Bureau of Construction to enter into a contract with Pike Industries Inc., Belmont, NH, for pavement rehabilitation, guardrail improvements and drainage improvements on 1.8 miles of US Route 3 in Stratford, on the basis of a low bid of $2,277,200. (2)Further authorize a contingency in the amount of $227,720 for payment of latent conditions which may appear during the construction of the project. Effective upon G&C approval through October 12, 2012. 100% Federal Funds.

Amount
$2.3M
$2,277,200, $227,720
Vendor
Pike Industries Inc.
Belmont, NH
Funding Source
100% Federal Funds
Vote Record approved
Motion by Sununu, seconded by Burton authorized the
Raymond Burton (R) yes
Daniel St. Hilaire (R) yes
Christopher Sununu (R) yes
Raymond Wieczorek (R) yes
Dave Wheeler (R) yes
← Back to Feb 22, 2012 meeting