Meetings / Jan 26, 2022 / Item 43

Item 43

approved contract late item

Jan 26, 2022

Description

Authorize the Bureau of Construction to enter into a contract with Evroks Corporation, Northfield, NH, for bridge rehabilitation in Manchester of Huse Road over I-293 and NH Rt. 101, on the basis of a single bid of $3,070,680.10. (2)Further authorize a contingency in the amount of $307,068.01 for payment of latent conditions which may appear during the construction of the project. Effective upon G&C approval through November 18, 2022. 100% Federal Funds.

Amount
$3.1M
$3,070,680.10, $307,068.01
Vendor
Evroks Corporation
Northfield, NH
Funding Source
100% Federal Funds
Vote Record approved
Joseph Kenney (R) yes
Cinde Warmington (D) yes
Janet Stevens (R) yes
Ted Gatsas (R) yes
Dave Wheeler (R) yes