Meetings / Apr 6, 2022 / Item 82

Item 82

withdrawn contract

Apr 6, 2022

Description

Authorize the Division of Public Works Design and Construction to enter into a contract with Ray’s Electric and General Contracting, Inc., Berlin, NH, for a total price not to exceed $2,047,000 for the Re-bid Highway Maintenance Facility, Colebrooke/Dixville, NH. (2) Further authorize the amount $75,000 be approved for payment to the Department of Administrative Services, Division of Public Works Design and Construction, for engineering services provided, bringing the total to $2,122,000. Effective upon G&C approval through November 1, 2022. 100% Highway Funds.

Amount
$2.1M
$2,047,000, $75,000, $2,122,000
Funding Source
100% Highway Funds
Vote Record withdrawn
Motion by Kenney, seconded by Warmington acted as follows
Joseph Kenney (R) yes
Cinde Warmington (D) yes
Janet Stevens (R) yes
Ted Gatsas (R) yes
Dave Wheeler (R) yes

Documents (1)

Item_82.pdf Open in new tab →
← Back to Apr 6, 2022 meeting