Item 40
approved contractFeb 5, 2025
Description
Authorize the Bureau of Construction to enter into a contract with B.U.R. Construction, LLC, Newport, NH, on the basis of a low bid of $23,054,582.88 for reconfiguration of the “dog-leg” intersection of US 202, NH 124 and NH 137 in Jaffrey, NH. (2) Further authorize a contingency in the amount of $1,613,820.80, for payment of latent conditions which may appear during the construction of the project. Effective upon G&C approval through June 30, 2028, unless amended by the Department in accordance with the Standard Specifications. 100% Federal Funds
Amount
$23.1M
$23,054,582.88, $1,613,820.80
Department
DEPARTMENT OF TRANSPORTATION
Funding Source
100% Federal Funds
Vote Record
approved
Motion by Kenney, seconded by Stevens acted as follows
Joseph Kenney
(R)
yes
Karen Liot Hill
(D)
yes
Janet Stevens
(R)
yes
John Stephen
(R)
yes
Dave Wheeler
(R)
yes