Meetings / Sep 7, 2022 / Item 115

Item 115

approved report

Sep 7, 2022

Description

Authorize the Division of Public Works Design and Construction to enter into a contract with D.L. King & Associates, Inc., Merrimack, NH, for a total price not to exceed $4,279,438 for REBID SMR Addition to Building M, Concord, NH. Effective upon G&C approval through October 27, 2023. 100% Federal Funds. (2) Further authorize that a contingency in the amount of $216,662 be approved for unanticipated site expenses for REBID SMR Addition to Building M, Concord, NH, bringing the total to $4,496,100. 100% Federal Funds. (3) Further authorize the amount of $77,000 be approved for payment to the Department of Administrative Services, Division of Public Works Design and Construction for engineering services provided, bringing the total to $4,573,100. 100% Federal Funds.

Amount
$4.6M
$4,279,438, $216,662, $4,496,100, $77,000, $4,573,100
Vendor
D.L. King & Associates, Inc.
Merrimack, NH
Funding Source
100% Federal Funds; 100% Federal Funds; 100% Federal Funds
Vote Record approved
Motion by Kenney, seconded by Stevens acted as follows
Joseph Kenney (R) yes
Cinde Warmington (D) yes
Janet Stevens (R) yes
Ted Gatsas (R) yes
Dave Wheeler (R) yes

Documents (1)

Item_115.pdf Open in new tab →
← Back to Sep 7, 2022 meeting