Meetings / Sep 21, 2022 / Item 45

Item 45

approved contract

Sep 21, 2022

Description

Authorize to enter into a contract agreement with JBC Construction LLC, Londonderry, NH, in the amount not to exceed $57,775, for office enlargement at the Plymouth Readiness Center. (2) Further authorize a contingency in the amount of $10,000 for unforeseen conditions and/or owner-initiated changes for the construction, bringing the total to $67,775. Effective upon G&C approval through April 30, 2023. 50% Federal Funds and 50% General Funds.

Amount
$67,775
$57,775,, $10,000, $67,775
Vendor
JBC Construction LLC
Londonderry, NH
Funding Source
50% Federal Funds and; 50% General Funds
Vote Record approved
Motion by Wheeler, seconded by Kenney acted as follows
Joseph Kenney (R) yes
Cinde Warmington (D) yes
Janet Stevens (R) yes
Ted Gatsas (R) yes
Dave Wheeler (R) yes

Documents (1)

Item_45.pdf Open in new tab →
← Back to Sep 21, 2022 meeting