Meetings / Jan 15, 2025 / Item 24

Item 24

approved contract

Jan 15, 2025

Description

Authorize the Bureau of Construction to enter into a contract with R.S. Audley, Inc., Bow, NH, on the basis of a low bid of $4,684,000.06, for replacement of the bridge carrying US 4 over Blackwater River in Andover, NH. (2) Further authorize a contingency in the amount of $374,720.01 for payment of latent conditions, which may appear during the construction of the project. Effective upon G&C approval through May 15, 2026, unless amended by the Department in accordance with the Standard Specifications. 100% Federal Funds

Amount
$4.7M
$4,684,000.06, $374,720.01
Vendor
R.S. Audley, Inc.
Bow, NH
Funding Source
100% Federal Funds
Vote Record approved
Motion by Kenney, seconded by Liot Hill acted as follows
Joseph Kenney (R) yes
Karen Liot Hill (D) yes
Janet Stevens (R) yes
John Stephen (R) yes
Dave Wheeler (R) yes

Documents (1)