Item 125
approved contractOct 30, 2024
Description
Authorize the Division of Public Works Design and Construction to enter into an amendment to an existing contract with PC Construction Company, South Burlington, VT (originally approved by G&C on 6/28/23, Item #277), by increasing the price limitation by $2,341,244.52 for a total price not to exceed $45,381,484.66 for the project ARPA Secure Psychiatric Unit Forensic Hospital, Concord, NH, and by extending the completion date from December 31, 2025 to February 5, 2026. (2) Further authorize a contingency in the amount of $50,000 for unanticipated expenses, bringing the total to $45,431,484.66. Effective upon G&C approval through February 5, 2026. 100% Federal Funds
Amount
$45.4M
$2,341,244.52, $45,381,484.66, $50,000, $45,431,484.66
Department
DEPARTMENT OF ADMINISTRATIVE SERVICES
Funding Source
100% Federal Funds
Effective Dates
December 31, 2025 — February 5, 2026
Vote Record
approved
Motion by Gatsas, seconded by Kenney acted as follows
Joseph Kenney
(R)
yes
Cinde Warmington
(D)
yes
Janet Stevens
(R)
yes
Ted Gatsas
(R)
yes
Dave Wheeler
(R)
yes
Documents (1)
Item_125.pdf