Item 132
approved contractOct 30, 2024
Description
Authorize the Division of Public Works Design and Construction to enter into a sole source amendment to an existing contract with D.L. King & Associates, Inc., Merrimack, NH (originally approved by G&C on 1/18/23, Item #117), by increasing the price limitation by $742,962.59 for a total price not to exceed $3,595,792.59 for Air Handler & Ductwork Replacement State Prison for Men, Concord, NH. Effective upon G&C approval through September 15, 2025, unless extended in accordance with the contract terms. 100% Federal Funds
Amount
$3.6M
$742,962.59, $3,595,792.59
Department
DEPARTMENT OF ADMINISTRATIVE SERVICES
Funding Source
100% Federal Funds
Vote Record
approved
Motion by Gatsas, seconded by Kenney acted as follows
Joseph Kenney
(R)
yes
Cinde Warmington
(D)
yes
Janet Stevens
(R)
yes
Ted Gatsas
(R)
yes
Dave Wheeler
(R)
yes
Documents (1)
Item_132.pdf
Open in new tab →