Item 22
approved contractOct 16, 2024
Authorize the Bureau of Highway Design to retroactively amend a contract with McFarland-Johnson, Inc., Concord, NH (originally approved by G&C on 4/21/21, Item #26), to perform additional final design to address transportation system needs along approximately 8.2 miles of the F.E. Everett Turnpike corridor in the City of Nashua, NH beginning about 0.2 miles north of Tinker Road overpass and proceeding north into the Town of Bedford, NH to approximately 1.2 miles north of the Bedford Road overpass (Exit 12 in the Town of Merrimack, NH), by extending the completion date from July 31, 2024 to March 31, 2026. (2) Further authorize to increase the fee in the amount of $1,080,500.30, from $9,869,680.83 to $10,950,181.13. Effective upon G&C approval. 100% Turnpike Funds