Meetings / Sep 25, 2024 / Item 49

Item 49

approved contract

Sep 25, 2024

Description

Authorize the Bureau of Construction to enter into a contract with Northeast Earth Mechanics, LLC, Pittsfield, NH, on the basis of a sole bid of $18,771,486.75 for construction of sound abatement walls and privacy fence along I-95 in Portsmouth, NH. (2) Further authorize a contingency in the amount of $938,574.34 for payment of latent conditions, which may appear during the construction of the project. Effective upon G&C approval through October 3, 2025. 100% Federal Funds

Amount
$18.8M
$18,771,486.75, $938,574.34
Vendor
Northeast Earth Mechanics, LLC
Pittsfield, NH
Funding Source
100% Federal Funds
Vote Record approved
Motion by Stevens, seconded by Kenney acted as follows
Joseph Kenney (R) yes
Cinde Warmington (D) yes
Janet Stevens (R) yes
Ted Gatsas (R) yes
Dave Wheeler (R) yes

Documents (1)

Item_49.pdf Open in new tab →