Item 188
approved contractSep 25, 2024
Authorize the Division of Public Works Design and Construction to enter into a sole source amendment to an existing contract with HDR Architecture, Inc., Omaha, NE (originally approved by G&C on 6/14/23, Item #174), by increasing the price limitation by $471,387 for a total price not to exceed $2,105,952 for design and construction administration services for the ARPA Youth Development Center Replacement, New Hampshire. (2) Further authorize a design contingency in the amount of $100,000 for unanticipated expenses, bringing the total to $571,387. (3) Further authorize a payment of $46,295 to the Department of Administrative Services, Division of Public Works Design and Construction, for engineering services provided, bringing the total amount to $617,682. Effective upon G&C approval through the completion of construction administrative services, estimated to be July 31, 2026. 100% Federal Funds