Item 79
approved contractJul 24, 2024
Authorize the Division of Public Works Design and Construction to enter into a contract with Jeremy Hiltz Excavating, Inc., Bristol, NH, for a total price not to exceed $264,925, for Wastewater System Improvements. 100% Federal Funds. (2) Further authorize a contingency in the amount of $35,000 for unanticipated site expenses, bringing the total to $299,925. 100% Capital Funds. (3) Further authorize a payment of $35,000 to the Department of Administrative Services, Division of Public Works Design and Construction, for engineering services provided, bringing the total to $334,925. Effective upon G&C approval through the completion of the construction administration services, estimated to be December 6, 2024, unless extended in accordance with the contract terms. 100% Federal Funds