approved contract

Dec 17, 2025

Description

Authorize the Bureau of Construction to enter into a contract with Vermont Recreational Surfacing & Fencing, Inc., Monroe, NH, on the basis of a low bid of $2,056,271.50 for guardrail replacement and updates on US Route 3 in Pittsburg, NH. (2) Further authorize a contingency in the amount of $205,627.15 for payment of latent conditions which may appear during the construction of the project. Effective upon G&C approval through September 18, 2026, unless amended by the Department in accordance with the Standard Specifications. 100% Federal Funds

Amount
$2.1M
$2,056,271.50, $205,627.15
Funding Source
100% Federal Funds
Vote Record approved
Motion by Stevens, seconded by Kenney acted as follows
Joseph Kenney (R) yes
Karen Liot Hill (D) yes
Janet Stevens (R) yes
John Stephen (R) yes
Dave Wheeler (R) yes