Authorize the Bureau of Construction to enter into a contract with Brox Industries, Inc., Dracut, MA, on the basis of a low bid of $4,737,723.86 for 7.8 miles of roadway resurfacing on NH 28/NH 28B in Salem, Windham, and Derry, NH. (2) Further authorize a contingency in the amount of $236,886.19 for payment of latent conditions, which may appear during the construction of the project. Effective upon G&C approval through September 20, 2024. 100% Federal Funds

Amount
$4.7M
$4,737,723.86, $236,886.19
Vendor
Brox Industries, Inc.
Dracut, MA
Funding Source
100% Federal Funds
Vote Record approved
Motion by Gatsas, seconded by Stevens acted as follows
Joseph Kenney (R) yes
Cinde Warmington (D) yes
Janet Stevens (R) yes
Ted Gatsas (R) yes
Dave Wheeler (R) yes