Item 103
approved amendmentFeb 21, 2024
Description
Authorize to retroactively amend an American Rescue Plan Act grant to the City of Portsmouth (originally approved by G&C on 1/18/23, Item #91), NH, by extending the completion date from December 31, 2023 to June 30, 2025, for the Fleet Street Roadway Reconstruction Phase I project. Effective upon G&C approval. This is a no cost time extension. 100% Federal Funds
Department
DEPARTMENT OF ENVIRONMENTAL SERVICES
Funding Source
100% Federal Funds
Effective Dates
December 31, 2023 — June 30, 2025