approved contract late item

Nov 8, 2023

Description

Authorize the Bureau of Construction to enter into a contract amendment with RJ Olszak Construction, Inc. d/b/a All-Ways Wrecking, Bridgewater, NH (originally approved by G&C on 6/28/23, Item #85), by increasing the contract amount by $200,000 from $907,500 to $1,107,500 for expansion and repurposing of the existing paved area, formerly used by the DMV for commercial vehicle inspection, to accommodate CDL testing at the Southbound Rest Area/Weight Station north of Exit 18 on I-89. Effective upon G&C approval. 100% Other Funds

Amount
$1.1M
$200,000, $907,500, $1,107,500
Funding Source
100% Other Funds
Vote Record approved