Meetings / Nov 8, 2023 / Item 52

Item 52

approved contract late item

Nov 8, 2023

Description

Authorize the Bureau of Construction to enter into a contract with Evroks Corporation, Northfield, NH, on the basis of a low bid of $1,328,109.90 for bridge preservation of three bridges in Marlborough, NH. (2) Further authorize a contingency in the amount of $132,810.99 for payment of latent conditions, which may appear during the construction of the project. Effective upon G&C approval through October 25, 2024. 100% Federal Funds

Amount
$1.3M
$1,328,109.90, $132,810.99
Vendor
Evroks Corporation
Northfield, NH
Funding Source
100% Federal Funds
Vote Record approved
Motion by Kenney, seconded by Wheeler acted as follows
Joseph Kenney (R) yes
Cinde Warmington (D) yes
Janet Stevens (R) yes
Ted Gatsas (R) yes
Dave Wheeler (R) yes

Documents (1)

Item_52.pdf Open in new tab →