Meetings / Nov 8, 2023 / Item 105

Item 105

approved contract late item

Nov 8, 2023

Description

Authorize to amend a contract with F.L. Merrill Construction Inc., Loudon, NH (originally approved by G&C on 9/13/17, Item #65), to continue construction services on the Suncook River Mitigation Project by extending the completion date from December 31, 2023 to December 31, 2028 and reducing the contract amount by $59,300 from $2,616,728 to $2,557,428. Effective upon G&C approval through December 31, 2028. This is a no cost time extension. 100% Capital (General) Funds

Amount
$2.6M
$59,300, $2,616,728, $2,557,428
Vendor
F.L. Merrill Construction Inc.
Loudon, NH
Funding Source
100% Capital (General) Funds
Effective Dates
December 31, 2023 — December 31, 2028
Vote Record approved
Motion by Wheeler, seconded by Kenney acted as follows
Joseph Kenney (R) yes
Cinde Warmington (D) yes
Janet Stevens (R) yes
Ted Gatsas (R) yes
Dave Wheeler (R) yes

Documents (1)

Item_105.pdf Open in new tab →
← Back to Nov 8, 2023 meeting