Item 25
approved contractSep 6, 2023
Description
Authorize the Bureau of Highway Design to enter into a sole source amendment to an existing contract with Vanasse Hangen Brustlin, Inc., Bedford, NH (originally approved by G&C on 6/30/21, Item #84), for intersection improvements in the Town of Jaffrey, NH, by extending the completion date from September 30, 2023 to June 30, 2028. (2) Further authorize increasing the fee by $492,773.58 from $2,162,892.27 to $2,655,655.85. Effective upon G&C approval. 100% Federal Funds
Amount
$2.7M
$492,773.58, $2,162,892.27, $2,655,655.85
Department
DEPARTMENT OF TRANSPORTATION
Funding Source
100% Federal Funds
Effective Dates
September 30, 2023 — June 30, 2028
Vote Record
approved